国家投资土地开发整理项目实施管理暂行办法 Interim Measures for the Implementation Management of State-Invested Land Devel

2009-03-24 法律英语 来源:互联网 作者:
l competent administration of state land resources of county level for self-examination of the project completion, arrange the relevant materials and make preparations for the acceptance examination upon completion of the project.

  The acceptance examination upon completion of the project shall be executed in compliance with the relevant provisions of the Interim Measures for Acceptance Examination upon the Completion of the State-invested Land Development Rectification Projects (GuiTuZiFa [2003] No.21)。

  Article 20 The undertaking unit of projects shall according to the relevant provisions timely collect and arrange the relevant documents, materials and graphics during the project implementation, set up and perfect the project archives, and timely submit the project archives to the local competent administration of state land resources of county level for filing after the acceptance examination upon completion of the project.

  Chapter V Supervisions and Inspection

  Article 21 Various levels of the competent administration of state land resources shall set up the supervisions and inspection system with the project progress, engineering quality, capital utilization, and construction of honest government, thus, investigating and solving material issues during project implementation.

  Article 22 Various levels of the competent administration of state land resources shall according to the relevant laws and regulations correct the misbehaviors during the project implementation and investigation on the responsible persons in breach of law and disciplines. Those involved in serious circumstances that constitute a crime shall be transferred for prosecution of criminal responsibilities by the judicial organs according to the relevant laws.

  Article 23 Any unit and individual is entitled to make reports, petitions or claims on the quality incidents and quality defects of the construction engineering of the projects.

  Chapter VI Supplementary Provisions

  Article 24 The implementation management of the land development rectification projects invested by local government sha

ll be executed by reference with these Measures.

  Article 25 The funding management for project implementation shall be executed in compliance with the relevant provisions of The Interim Measures for Funding Management of Land Development Rectification Projects (GuoTuZiFa [2000] No. 282)。

  Article 26 The Measures shall come into force as of the date of promulgation